A Mechanic's Lien
is a legal device, which, when filed properly, gives the
lienor (contractor, subcontractor, or materialman) a legal
claim against the real property upon which the project is
located.
These differences
include:
Private
Lien:
- Filed in the
County Clerk's office in the county of the project's
location.
- Is a legal claim
against the real property upon which the project is based.
- Liens must be
filed at any time during the progress of work and
furnishing of materials, or within eight months after the
final performance of work or furnishing of materials,
except that on single4amily dwellings, the lienor must
file within four months after the final performance of
work or furnishing of materials.
- Liens will expire
one (1) year after the day of Notice of Lien has been
filed unless (a) a Notice of Extension is filed extending
the lien for an additional year, (b) an action is
commenced to foreclose the lien, (c) or unless a court
order is entered continuing the lien for a period not
exceeding one year.
- Proof of service
on owner, contractor and subcontractor must also be filed
within 35 days.
Public
Improvement Lien:
- Filed with the
head of the public agency having charge of the
construction and the State Comptroller or financial
officers of the public corporation.
- Is a claim
against the public funds allocated to the construction or
demolition of the public improvement.
- Liens will expire
six months after the date of filing the Notice of Lien
Unless (a) a Notice of Extension is filed extending the
lien for an additional year, (b) an action is undertaken
to foreclose or (c) unless order is entered continuing the
lien for a period not exceeding one year.
- Proof of service
on Owner, contractor and subcontractor must also be filed
with the Notice of Lien.
Property owned by
the federal government is not subject to the New York State
Mechanic's Lien Law.
Bonding
Off a Lien
The owner or
contractor may execute a bond with an insurance company
(surety) and obtain an order from the New York State Supreme
Court discharging the lien upon the filing of that bond.
Generally, the amount of the bond is set at the amount of the
lien plus 10%.
Notwithstanding the
filing of the bond to discharge the lien, the claimant must
bring an action to foreclose the private or public improvement
lien in order to claim against the bond.
Payment
Bonds
On municipal
projects in the state of New York the prime contractor is
required to file a labor and material bond with the
municipality guaranteeing that all persons providing labor and
materials will be paid.
On such bonded jobs,
a subcontractor or supplier may file a claim against the bond
if the contractor fails to make payment. In the event that the
subcontractor or supplier does not have a direct contractual
relationship with the contractor, then the claimant is
required to provide notice of the claim to the prime
contractor within 120 days of the last labor or material on
the job.
A court action to
enforce a claim against the bond must be commenced within one
(1) year from the date on which final payment became due.
Similar procedures pertain to federal projects under the
Miller Act.
Please
contact us if you are unable to access the forms provided in
this section (RTF files), or if you have any questions
regarding the usage of these forms.